An Introduction to
PMPlan Enterprise


A "Free" Limited, but a
Fully-Functional
Evaluation Edition of
PMPlan Standard


To Purchase the
PMPlan License Key


To Download Current
PMPlan Update!


A Guide to Using
PMPlan Standard


To Download Current
PMPlan Enterprise
Help & Manual Updates

 

 


Credit Card Services


Web Design

 

AlNik Solutions, LLC
E-mail: alnik@pmplan.com

©2003/2007 - All rights reserved
.

AlNik Solutions

AlNik Solutions©

PMPlan©

Enterprise Software Tools
For Project Management, and
Workforce Planning and Forecasting!

"Designed for Project Managers by Project Managers"

Aligned with the Principles of the ANSI/EIA-748-A-1998 Standard
for
Earned Value Management (EVM)




Where PMPlan Software can help with meeting ANSI/EIA-748-A-1998 “Earned Value Management Systems”

ANSI Criteria[1]{1}
Ref No {2}
PMPlan Standard
PMPlan Enterprise
Define the authorized work elements for the program (Work Breakdown Structure (WBS))
2.1a
Yes
Yes
Identify the program organizational structure (OBS) (Who is responsible for accomplishing the work)
2.1b
Yes
Yes
WBS and OBS Integration
2.1c
No
Yes
Overhead Control
2.1d
Partial{4}
Yes
Control Account Plan Creation
2.1e
Yes
Yes
Schedule Work
2.2a
Yes
Yes
Identify progress indicators
2.2b
Yes
Yes
Time-Phased Budget Baseline
2.2c
Yes
Yes
Project Budget
2.2d
Yes
Yes
Work Packages measurable units
2.2e
Yes
Yes
Authorized Budgets
2.2f
Yes
Yes
Level of Effort
2.2g
Yes
Yes
Overhead Budgets
2.2h
No
Yes
Identify management reserves and undistributed budget
2.2i
Yes
Yes
Program Target Cost Goal
2.2j
Yes
Yes
Measure Direct Costs
2.3a
Yes{5}
Yes{5}
Control Account maps to only one WBS element
2.3b
Yes
Yes
Control Account maps to only one OBS element
2.3c
No
No
Measure Indirect Costs
2.3d
No
Yes
Production or Development Quantity Costs
2.3e
Yes
Yes
Accumulated and Material Costs
2.3f
Yes
Yes
Monthly generate Schedule and Cost Variances
2.4a
Yes
Yes
Comprehensive Variance Analysis
2.4b
No
Yes
Indirect Cost Analysis
2.4c
No
No
WBS and OBS Variance Analysis
2.4d
Yes
Yes
Corrective Actions
2.4e
No
Yes
Estimate at Complete Reconciliation
2.4f
Yes
Yes
Timely Changes
2.5a
Yes
Yes
Reconcile Budgets
2.5b
Yes
Yes
Baseline Integrity
2.5c
Partial{6}
Partial{6}
Rebaseline Processes
2.5d
Yes
Yes
Baseline Traceability
2.5e
Partial{7}
Yes

 

References:
[1] “Earned Value Management Systems”, EIA Standard, ANSI/EIA-748-A-1998
[2] Fleming, Quentin W. and Koppelman, Joel M. “Start With ‘Simple’ Earned Value On All Your Projects” CrossTalk The Journal of Defense Software Engineering, June 2006 (http://www.stsc.hill.af.mil/CrossTalk/2006/06/0606FlemingKoppelman.html)

Notes:
{1} The list of 32 EVMS guidelines criteria noted in the ANSI 748 standard.
{2} Refer to the reference section in the ANSI 748 standard.
{3} These criteria (based on Fleming and Koppelman article) are the minimum requirements to make effective use of EVMS methods without using the full set required for large complex projects.
{4} PMPlan Standard only has base rate and rate factor which are not tracked separately.
{5} Each tool can store direct costs by manually inputting the costs from reports generated by the general books of account or import the costs from files generated by the general books of account.
{6} This process is controlled by stated policy.
{7} Only the previous baseline is maintained within the project file. To save multiply baselines requires saving renamed project files to keep a history of multiply baselines.

 

 