PMPlan Enterprise

PMPlan Enterprise is the project management tool that is strictly used concurrently with other users on a server based ‘MS SQL Server’ database platform. PMPlan Enterprise can also be used on a local or server based ‘MS SQL Server Express’ database platform with some user limitations, and will handle 5,000 resources within 32,000 work elements for a plan period of up-to 10 years (+/-,  and limited only by the amount of installed memory, and in some cases 32 bit vs. 64 bit processing). The PMPlan Enterprise tool does meet with the Defense Contract Audit Agency (DCAA) standards, and other Government standards for those projects requiring a fully mandated pricing support and EVM capability. The PMPlan Enterprise pricing and proposal supporting documentation is an integral component to the pricing process approved for use by a division of General Dynamics.

PMPlanPro is a significant upgrade to PMPlan suite of tools in that it can be used as a stand-alone application, similar to PMPlan Standard, using a ‘SQL Server Express’ database, or it may be used in an Enterprise mode concurrently with other users as an additional user seat on a server based ‘MS SQL Server’ database platform. PMPlan Pro can be structured to be able to check-out an Enterprise project file from the server, work with the plan or negotiate with a client off-site, and then return the revised/negotiated project plan to the Enterprise server. PMPlanPro handles 5,000 resources within 32,000 work elements for a plan period of up-to 10 years (+/-, limited only by the amount of installed memory, and in some cases 32 bit vs. 64 bit processing). The PMPlanPro tool, when used in the Enterprise mode, can meet the standards of the Defense Contract Audit Agency (DCAA), and meets other Government standards for those projects requiring a fully mandated pricing support and EVM capability

PMPlan Enterprise Tools: support project management and line management teams in providing for concurrent and timely access to a centralized common project and workforce resource database by all project teams, for all projects, expediting and improving the processing of project and workforce financial and schedule forecast data.

  • The project management tool, PMPlan Enterprise, an enhanced version of the stand-alone PMPlan standard, and with the exception of the resource pool, looks and works the same as PMPlan. However, PMPlan Enterprise contains additional features not available in PMPlan such as the ability to define project rules, develop Burden Rate tables, etc. PMPlan Enterprise can be customized to access specific project financial and forecasting data of other applications and organizational databases and/or other unique management processes, allowing for additional and more comprehensive Earned Value Management EVM) and other reporting requirements.
  • The line management tool, LMPlan, is a workforce assignment and forecasting tool for billable and un-billable project and overhead applications. It provides for the set up its own project file for limited purposes, or may import project plans from the Enterprise project management tool, PMPlan Enterprise, or other in house project or pricing tools, either directly or indirectly.
  • All sensitive information contained in the centralized database is managed, with controlled access, through another limited access Enterprise tool, anDBManager.
  • A Management focused Revenue and Portfolio tool, PMFolio provides for the analysis of the project data stored within the centralized server database, and provides summary reports that determine the status and health of all of the projects within the database, or of selected projects of interest.

The PMPlan Enterprise tools provide the project and line managers with compatible tools that, when jointly applied to the common data within the centralized database, provides for timely project status reports and summary data support for the administration and forecasting of the workload and workforce requirements on the total organizational human resource pool defined within the database.

The 'PMPlanDatabase' contains all of the tables used by PMPlan Enterprise, PMPlanPro, LMPlan, and PMFolio. The 'PMPlanDatabase' is attached to an independently purchased and installed Microsoft SQL Server™ on the organization's network server, and is managed by anDBManager. anDBManager can be installed on any MS Windows® or Apple Intel based Mac® compatible computer.

PMPlan Enterprise© - the PMPlan Enterprise server based version of the PMPlan EVM Project Management software tool.


PMPlan Enterprise, with the exception of the resource pool, looks and works the same as PMPlan, but the application contains additional features not available in PMPlan such as a the ability to define project rules, develop Burden Rate Tables, use the common Resource Pool, and can define project specific holidays and override normal non-workdays. Resource loading, which is stored at daily level, is done from task level with automatic roll up to the cost center and the project. PMPlan Enterprise incorporates import/export capabilities for other applications including PMPlan, MS Project®, Microframe's MPM® and ProPricer®. PMPlan Enterprise can be customized to interface with additional modules (not included with this application), custom designed to access specific project and forecasting data of other applications and/or organizational databases allowing for additional and more comprehensive Earned Value Management (EVM) reporting. This application can be installed on any of the site’s Windows® compatible computers, and includes twenty (20) licensed user seats that can be concurrently connected to the database (Note: additional licensed concurrent seats can be purchased).

Some example PMPlan “Input Forms” are:

PMP2_WBS Tree2.bmp

1 – PMPlan Enterprise Project Work Plan


PMP2_Logic.bmp

2 - PMPlanEnterprise Project Logic Network


GanttScheduleTab.png

3 – PMPlan Enterprise Project Schedule

PMP2_Resource.bmp

4 – PMPlan Enterprise Project Resources


PMP2_TotEffort.bmp
5 – PMPlan Enterprise Project Total Effort

PMP2_ResEffort.bmp
6 – PMPlan Enterprise Project Resource Effort

PMP2_ActEffort.bmp

7 – PMPlan Enterprise Project Activity Effort

 

PMP2_TrSetupt.bmp

8 – PMPlan Enterprise Project Tracking


PMP2_Status.bmp

9 – PMPlan Enterprise Project Status

 

Contract Performance Report (CPR), five formats

PMPlanDB_CPR_Format1.png

CPR Format 1

PMPlanDB_CPR_Format2.png
CPR Format 2

PMPlanDB_CPR_Format3.png
CPR Format 3

PMPlanDB_CPR_Format4.png
CPR Format 4

PMPlanDB_CPR_Format5.png
CPR Format 5

 

Services:


AlNik Solutions offers Consulting Support for systems interfacing, integration, software Training and SQL Server and ’PMPlanDatabase’ support. In addition, AlNik Solutions offers an Annual Service & Maintenance Contract. PMPlan Enterprise tools are powerful project and resource management tools right out of the box, however, experience has shown that most customers have unique requirements for interfacing with, or exchanging data with, internal financial and HR data, and/or other corporate directed commercial applications (i.e. Deltek®, Microframe®, Microsoft®, ProPricer®, etc.). AlNik Solutions recognizes these requirements, and is in a position to provide customization of the PMPlan Enterprise application modules to address them.


Comparison of the Features of PMPlan©, PMPlanPro© and PMPlan Enterprise©

Features

PMPlan & PMPlanPro
as Standalone's

PMPlanPro
in Enterprise Mode

PMPlan
Enterprise

Interactive Master Work Breakdown Structure (MWBS) view development

Yes

Yes

Yes

Interactive Functional Work Breakdown Structure (FWBS) view development

Yes

Yes

Yes

Activities per Project

5,000

32,000

32,000

Milestones per Project

10,000

100,000

100,000

Can insert Intermediate Milestones

Yes

Yes

Yes

Can input narrative Objective/Scope per activity/task

32,000 characters

32,000 characters

32,000 characters

Can input Notes per activity/task

32,000 characters

32,000 characters

32,000 characters

Can input Basis of Estimate (BOE) per activity/task

32,000 characters

32,000 characters

32,000 characters

Tracks Deliverables

Yes

Yes

Yes

Generate a rich text file of the WBS with objectives, notes, and other information in Outline form for import into most word processors.

Yes

Yes

Yes

Custom Fields including Calculations

Yes

Yes

Yes

Schedule Risk Assessment

Yes

Yes

Yes

Cost Risk Assessment

Yes

Yes

Yes

Integrated Master Schedule (Graphic Gantt) view with project outline

Yes

Yes

Yes

Customizable Gantt Format

Yes

Yes

Yes

Smallest Scheduling Unit

1 day

1 day

1 day

Number of Auto-Formatted Levels in Gantt View

6

6

6

Customizable Calendars

5,000

32,000

32,000

Multiple Tasks on one row

Yes

Yes

Yes

Interactive Graphic Logic Network view

Yes

Yes

Yes

Logic Relationships with lead or lag

Yes

Yes

Yes

Logic Tracing Guide

Yes

Yes

Yes

Indirect Burden Rate Tables (O-head, G&A)

No

Yes

Yes

Salary Actions

Yes

Yes

Yes

Multi-Year Resource Rates

Yes

Yes

Yes

Works with Single Rate Factor

Yes

Yes

Yes

Define Pricing Types

No

Yes

Yes

Time and Material Rates

No

Yes

Yes

Resources (Labor and other Direct Costs)

Yes

Yes

Yes

Handle Job Categories and track cost variance between actual resource and job category rates

Yes

Yes

Yes

Multi-Level Resource Breakdown Structure (RBS)

No

Yes

Yes

Organizational Breakdown Structure (OBS)

No

Yes

Yes

Flat Auto-Spread of Resources

Yes

Yes

Yes

Front-End, Back-End etc. Auto Spreading

No

Yes

Yes

Custom Assign of Resources

Yes

Yes

Yes

Interactive Resource Total Loading Table (Row – WBS elements / Columns – Resources). This feature allows rapid initial costing of project)

Yes

Yes

Yes

Costs and Resource Rollup to upper levels

Yes

Yes

Yes

Always see Total Project Cost when resource loading

Yes

Yes

Yes

Prevents Resource Loading at upper levels

Yes

Yes

Yes

Interactive Resource Loading by Individual Table resource (Rows – WBS elements / Columns – Periods (daily, weekly, or monthly)

Yes

Yes

Yes

Auto-leveling of resources

Intentionally
No! *

Intentionally
No! *

Intentionally
No! *

Resource Driven Activity Duration

Yes

Yes

Yes

Level (move) Resource over-allocation from one resource to other resources

Yes

Yes

Yes

Number of colors displayed for allocation levels

6

6

6

Loading views can display Full Time Equivalents

Yes

Yes

Yes

Material Details per activity with Description, Vendor, Part Id, Unit Type, Cost per unit, Basis, and Quantity by Period.

Yes

Yes

Yes

Travel Details per activity with Travel between, Persons per trip, Days per trip, Airfare per person, Per Diem per person, Ground costs per trip (car rental, taxi, etc.), Basis, and Quantity by Period

Yes

Yes

Yes

Easy to Schedule Multi-Resources per activity

Yes

Yes

Yes

Can define Cost Accounts/Work Packages

Yes

Yes

Yes

Can flag Deliverables and provide report

Yes

Yes

Yes

Can add Custom Fields

Yes

Yes

Yes

Co-actions, or Hammock Tasks

No

Yes

Yes

Graphic Spend Plan

Yes

Yes

Yes

Define weekly workdays

Yes

Yes

Yes

Generate a Work Authorization Statement for each Work Package Subaccount with objective, deliverables, schedule, and budget, which becomes an internal contract between the Project Manager and the Work Package Leader

Yes

Yes

Yes

Provides Earned Value Methodology

Yes

Yes

Yes

Can insert Earned Value Milestones

Yes

Yes

Yes

Contract Performance Report (CPR – 5 Formats) - DoD-I-5000.2

Formats 1&5

All

All

Generates Graphic Performance Report that plots Planned, Earned, and Actual Costs versus time. Also, plots Cost and Schedule Performance Indices

Yes

Yes

Yes

Estimate-At Completion (EAC) Snapshots

No

Yes

Yes

EAC History Chart

No

Yes

Yes

Historical Baselines

No

Yes

Yes

Proposal Pricing and Documentation per DCAA Standards

No

Yes

Yes

Auto-Creation of Slide Set Presentation

Yes

Yes

Yes

Auto-Creation of Report Sets into one Report

Yes

Yes

Yes

Create Invoicing Plan

No

Yes

Yes

Cash Flow Report

No

Yes

Yes

Customizable Reports

Yes

Yes

Yes

Can independently Summarize Multiple-Projects

No

Yes

Yes

Can Merge Project Files

No

Yes

Yes

Transfer table text to spreadsheet application

Yes

Yes

Yes

Multiple User Access to shared projects

No

Yes

Yes

Operates Stand Alone

Yes

Yes

No

Server Database (i.e. SQL Server)

No

Yes

Yes

Update of Schedule Status Via E-mail

Future

Future

Future

E-mail Distribution of project information

Future

Future

Future

OLE Automation

Yes

Yes

Yes

User-Definable Forms

Limited

Yes

Yes

User-Definable Toolbars

Yes

Yes

Yes

ODBC Connectivity

Yes

Yes

Yes

Import MS Project files (*.mpx ,*.mdb, and *.xml)

Yes

Yes

Yes

* AlNik considers this activity to be the responsibility of the project manager, not the software!

 

PMPlan “Enterprise” Purchasing and Pricing
PMPlan Enterprise products (PMPlan Enterprise©, anDBManager©, LMPlan© and PMFolio©) require a database interfaced with the independently purchased (customer supplied) organizational network installation of Microsoft’s SQL Server™, in order to function for multi user requirements. The organizations IT or database professional may need to be consulted to coordinate the use of, and/or the installation the MS SQL Server™, as well as the installation and maintenance of PMPlan Enterprise, anDBManager, LMPlan, and the associated ‘PMPlanDatabase’.

Information for the use and purchase of MS SQL Server™ may be obtained at:
http://www.microsoft.com/sql/prodinfo/default.mspx

The PMPlan Enterprise tools may be installed and operated as is, on a non-integrated, manually supported ‘PMPlanDatabase’. Our experience has been however, that as an Enterprise System, most of our client organizations look to the integration of the PMPlan Enterprise system into the organizations processes including accessing data, either directly or in-directly, from their HR and financial databases and providing feedback to their other processes. Some of these organizations require integration with already in-house pricing and analysis databases, and most customers already have procedural requirements in place for unique reporting process’ that may further require integration into the PMPlan Enterprise system.

Given all of the above, and noting that each customer’s unique integration, installation and customization requirements at installation, would rarely match that of others, the purchase of a PMPlan Enterprise System would not normally be an off-the-shelf process. Integration of a new system of process tools into organizations current processes and procedures, or a subset of these, would normally be the customers preferred approach. As a result, an analysis of the integration, and customization requirements of each individual customer would be pre-requisite to our making a formal quote to any customer.

PMPlan Enterprise is only available through processing a Request for Quote “RFQ”! To initiate the process of developing a quote for the installation, integration and customization of PMPlan Enterprise for your organization, please visit our “AlNik Solutions Store” for your request for quote (RFQ). We will then contact you, and begin the process.

PMPlan Enterprise’s Potential Competition and the Comparisons:
AlNik Solutions has not yet developed a detailed feature/function comparison chart for its potential competitors such as, Deltek’s Open Plan/Cobra, Oracle’s Primavera P6/Cost Manager, and Microsoft’s Project and its add-on applications, as well as many others; but we can however offer some comparison thoughts on the VALUE of PMPlan Enterprise.

We CAN tell you that PMPlan Enterprise has competed against the competition and has won primarily based on PMPlan’s intuitive processes and ease of use, its rich set of features and ability to do more in less time, versus the non-intuitive products of the competitors. The current mix of users of the PMPlan Enterprise products include Project Manager’s and Project Staff, PMO Managers and Staff, Line Managers and Administrators, Marketing, Contracting, and Financial Management and Staff, and Executive Management Staff. Currently, no additional fulltime staff have been required by our customers for operating the PMPlan software applications for project workload and workforce control, but some staff have been assigned to sensitive (HR, Financial and other) database administrative responsibilities.

With the government/industrial standards in mind, PMPlan tools are fully integrated applications, and are first, WBS (Work Breakdown Structure) focused, and resource based planning tools, using Integrated Scheduling with Precedence Logic Diagramming Method to identify and define the critical path of the project schedule, and to assess any risk developed as a result of the planned cost and schedule; whereas most of the competitive products, are not fully-integrated Scheduling and planning tools. Once the information is developed in some competitive applications, it is extracted from them and imported into other functional applications, such as pricing tools, and EVM tools for EVMS cost and performance analysis and reporting. The PMPlan Enterprise pricing and proposal supporting documentation is an integral component to the pricing process approved for use by a customer of AlNik Solutions. 

Some elements we would suggest to be included in a comparison:

  • A fully functional pricing tool to DCAA Standards, with the capability of having all DCAA approved supporting documentation filed within the PMPlan database and integrated with the project plan, including a full Basis of Estimate capability; or, if required, the full project resource loading details may be exported to a separate pricing tool with separate, non-integrated, pricing support documentation (i.e. ProPricer, MPM, etc.).
  • Flexibility in interfacing with other client associated applications and systems (i.e. financial costing, pricing, HR resources, and other policies and processes, etc.).
  • Ease of use (only gained through demonstration & reference checks). In many cases, competitive applications may require full-time project control staff, as reports indicate they may not be for the casual user.
  • Affordability without reducing value. One significant difference between PMPlan Enterprise tools and most of the competition is that there is no limit as to how many user computers the PMPlan Enterprise tools may be installed on. The only limit when using PMPlan Enterprise is the number of user seats that may access, and use the PMPlan database concurrently. 20 concurrent user seats are in the base price of PMPlan Enterprise which is normally adequate for about 100 total users. Additional concurrent user seats are available.
  • Workforce resource assignment and proactively controlled leveling.
  • Workforce resource forecasting of staff-time availability for current and future; billable work, proposal preparation, IR&D, other responsibilities for overhead activities, staff vacation, etc.
  • Executive / Management summary reporting (Portfolio) of all, or preferred workload requirements and performance, and the workload’s impact on billing and cash flow.

We are quite confident that through a web-demo and a hands-on evaluation and other discussions, we can convey the overall increased VALUE that PMPlan might bring to your organization, as compared to the competition. Our price is based on the concurrent user licensing method versus the competitions annual per user seat licensing method.

The greatest comparison of our product to the competition that we hear about, is that the PMPlan application is more intuitive to use, is the easiest to get information into and to obtain immediate results from, and has a wider range of desired features, especially when applied to tightly budgeted projects that require the lesser qualified resources to be involved with the project management software without the use of dedicated professional project management systems specialists.

What AlNik Solutions PMPlan Product Users Say!

    • "...I've reviewed dozens of PM software packages and yours is one of the easiest to get information into and has a wider range of desired features than most."
    • "...as a program manager, the application is so intuitive that I was able to develop my first plan without reference to help...!"
    • "...the budget screens can impart the global or detailed perspective with the superior features built into the user interface selections. This flexibility during time sensitive negotiations has been critical to proposal closure."
    • "...this program provides the complete package, and is not dependent on any other software investment, making PMPlan relative inexpensive when considering the cost associated with buying multiple packages to achieve the same result...!"
    • "...at last, a fully integrated project planning and management tool that is easy to assimilate without having to hire full-time project management systems specialists to support it....! "

     

 

 